Public Works Projects
Contact Info

North Mesa Road Improvements Phase 2

North Mesa Road Improvements Project Cumbres Del Sol Subdivision, Phase 2 will begin in late June with a completion of mid-September.

  • Camino Manzana will begin in late June
  • Camino Mora will begin in late July
  • Camino Cereza will begin in mid August.

Questions? / Comments: Please call the Public Works Department at 662-8150 or send an email to LACPW@lacnm.us

A public meeting will be held on Thursday March 1, 2018 at 5:30 p.m. in the Municipal Building at 1000 Central Avenue. Room 110

DP Road Infrastructure

DP Road Infrastructure

Infrastructure for the A-16 A Site needs to be installed first on DP Road as part of the project (funding for the water,  gas, sewer lines and electric lines is a separate economic development project).

Click here to view a map of the proposed infrastructure on DP Road that will serve A-8 A, A-8 B, and A-9 and will terminate at A-16. 

Golf Course Improvements Project

County staff working with the Parks and Rec Board devise a plan that implements the Capital Improvement Projects (CIP) Golf Course Improvements at a cost not to exceed $4.524 million and implement it over a multi-year period. 

The main goal of the Golf Course Project is to replace the irrigation system. All other elements will be prioritized and determined throughout the project. 

Preliminary Project Development Schedule:
Design - February 2018 - September 2018
Construction - September 2018 - March 2020

Pinon Splash Pad

County staff working with the Parks and Rec Board devise a plan that proposes a splash pad in White Rock at a cost not to exceed $720,000 with a request to lower that if at all possible. 

During the design and construction phases the team will consider all cost saving elements including the type of operating systems to provide the best product for the lowest cost. 

Preliminary Project Development Schedule:
Design - January 2018 - May 2018
Construction - May 2018 - November 2018

Ice Rink Improvements

County staff working with Parks and Rec Board devise a plan that proposes improvements to the existing outdoor ice skating rink for an amount approximately $1.2 million which will include a shade study.

Preliminary Project Development Schedule:
Shade study - December 2017 
Design - June 2018 - May 2019
Construction - June 2019 - October 2019

Kiddie Pool - (Adjacent to Aquatic Center)

The new $6.5 million Kiddie Pool with low entry zone, splash features, lazy river and slide. It will be built using County land on the eastern grassy slope of the existing center with access provided from the main center. Design will get underway in spring 2018.

The Kiddie Pool will not be authorized to move ahead to construction until the LANL operations and maintenance contract is awarded (expected April/May 2018).

Kiddie Pool