Bathtub Row Reconstruction Project Updates

Construction details for the week of October 28, 2024

Hours of Construction:

TLC Plumbing & Utility will continue work preparing for paving of the Fuller Lodge parking lots and the phase one portion of Bathtub Row, Juniper, and Oppenheimer Drive. Paving for this phase is scheduled to start Tuesday October 29 and will be complete prior to November 1.

Voting access at the Betty Eheart Senior Center will be available on November 1 through November 5 from Central Ave.

The full road closure will remain in effect on Bathtub Row from Central Avenue to Oppenheimer Drive (Mesa Public Library Driveway). Please continue to use the designated pedestrian path for access into and around Fuller Lodge, Museum and Art Center.

All questions, concerns, or special access needs should be sent to the Public Works Department at lacpw@lacnm.usor call 505-662-8150. Thank you for your cooperation and patience. For additional project details, visit the Public Works Department Bathtub Row Reconstruction Project webpage