Construction activity for the week of July 1, 2024

TLC Plumbing & Utility is working Monday through Wednesday, 7 a.m. to 5 p.m. TLC Plumbing and Utility will be off Thursday July 4, and Friday July 5 in observance of Independence Day.

Parking:

  • Parking will not be allowed south of DP Road outside of designated areas south of Ace Hardware and south of the Los Alamos Fire Training Academy.

Traffic Control:

  • Crews continue two trenching operations on DP Road to install electrical conduit as well as water and gas..
  • Follow all work zone signs and exercise caution; flaggers may direct traffic during certain construction events.
  • Access to businesses will be maintained; westbound traffic direction remains unchanged. 

All questions and concerns should be sent to the Public Works Department at lacpw@lacnm.us or call 505-662-8150. For additional project details, visit the Public Works Department DP Road Reconstruction Project.