DP Road Phase II Reconstruction Project Updates
Construction activity for the week of July 1, 2024
TLC Plumbing & Utility is working Monday through Wednesday, 7 a.m. to 5 p.m. TLC Plumbing and Utility will be off Thursday July 4, and Friday July 5 in observance of Independence Day.
Parking:
- Parking will not be allowed south of DP Road outside of designated areas south of Ace Hardware and south of the Los Alamos Fire Training Academy.
Traffic Control:
- Crews continue two trenching operations on DP Road to install electrical conduit as well as water and gas..
- Follow all work zone signs and exercise caution; flaggers may direct traffic during certain construction events.
- Access to businesses will be maintained; westbound traffic direction remains unchanged.
All questions and concerns should be sent to the Public Works Department at lacpw@lacnm.us or call 505-662-8150. For additional project details, visit the Public Works Department DP Road Reconstruction Project.