Cone Zone Updates
As of November 1, 2025, construction activity has slowed for the winter months. Most Cone Zone projects have wrapped up for the season; however, a few remain active. View current updates and traffic impacts for road construction projects and special events below. Click live links for mapped locations and detailed project information. Active projects will be updated as needed.
Essential services—including mail delivery, trash and recycling collection, and emergency response—will continue throughout each project. Residents and businesses may still experience large equipment and construction noise.
Motorists and pedestrians are reminded to use caution, reduce speed near work zones, and follow designated detour routes.
UPDATED February 20, 2026
Road and Utility Work:
Denver Steels Phase II Improvement Project Updates:
Construction activity for the week of February 23, 2026
TLC will continue working on Ridgeway Drive and 35th Street.
NOTE: Vehicles shall be removed from these roads during construction activities. (7 a.m. to 6 p.m., Monday through Friday)
Construction Operations
Ridgeway Drive (between 37th St. and 35th St.)
Crews will finalize installing new water lines, services, and meters.
Crews will begin re-grading the roadway.
Crews will begin installing curb and gutter.
35th St.
Crews will continue potholing and trenching for water lines.
Crews will continue installing water lines and water services
Questa Drive
Crews will continue potholing for water lines.
Crews will continue concrete removal.
Traffic Control:
During construction, road closures, lane restrictions, and detours will be in place.
Follow all work zone signs and exercise caution.
Access to residents will be maintained.
All questions and concerns should be sent to:
Public Works Department at lacpw@losalamosnm.gov, or call 505-662-8150
Department of Public Utilities at CustomerCare@losalamosnm.gov, or call 505-662-8333
For additional project details, visit the webpage:
Denver Steels Phase II Improvements Project
9th St. Sidewalk Improvement Project Starts February 25
The contractor, Franco Builders, will be in the area performing removal and replacement of sidewalk and curb on the west side of 9th St. from Myrtle Street to Iris Street. A partial road closure will be in effect on 9th. Parking along the west side of street will not be allowed in the areas of construction.
Construction work will be from 7 a.m. to 6 p.m., Monday through Friday. Residents can expect large equipment, and construction noise. To minimize disruption, the contractor will notify and coordinate with affected residents for certain construction logistics, and traffic changes as work progresses. Services such as mail delivery, trash and recycling collection, school bus, transit, and emergency services will be maintained.
Special Events:
None at this time.
Ongoing Projects:
Camp May Road closures for the Jemez Mountain Fire Protection Project, which includes installation of water pipeline and other service conduits up Camp May Road, will start up again starting February 23. The following will be closed per the schedule below: Camp May Road, Camp May, and adjacent trails.
- Feb. 23-27: traffic controls will be in place for a one-lane closure while contractor Dub-L-EE prepares for paving.
- Starting Mar. 2: road will be closed to the public from Monday morning through Thursday at 5 p.m. each week until further notice.
- March 16-19: the week of local spring break may be an exception to the closures depending on the weather. If Pajarito Mountain has enough snow to remain open for skiing, the road will be open for this week only.
Hill Apartments: Realignment of 35th Street at Trinity Drive (NM-502)/Pavilion Construction
Work to fix roads damaged in the course of underground utility repairs is pending for the following locations. Work is weather dependent and will be completed over several months.
- 7080 West Road - asphalt
- 33rd Street - asphalt
- 11 Rover - concrete
- Camino Uva (2 locations) - concrete
- 43rd Street - asphalt
- 45th Street near Alabama - concrete and asphalt
- 1045 Big Loop Rock - asphalt
- 945 Alamo - asphalt
- 514 Paige Loop - asphalt (summer)
- 533 Aragon - asphalt (summer)
- 360 Cheryl - asphalt (summer)
- Grand Canyon and Meadow sidewalk - concrete (summer)
-
Learn more about utility work impacting the roadway:
Utility Work Impacting Roadways
Learn more about other projects on the County Projects page:
County Projects